220 kV Van Tri - Soc Son line: Will be energized in February, 2013

(CPV) - In the morning of February 15, 2013, in Hong Ky commune, Soc Son district (Hanoi), the delegation of the National Power Transmission Corporation (EVNNPT) led by General Director Nguyen Manh Hung arrived. working and wishing Tet holiday to officials, engineers and workers on the construction site of the 220kV Van Tri - Soc Son transmission line.

Despite the cold and rainy weather, the contractor still urgently constructed and erected columns (Photo: Le Hoan)

Up to this point, the 220 kV Van Tri - Soc Son transmission line project is entering the sprint stage, construction and installation work is being focused on deploying at the last column position (position 99) on the route. wire. Representative of the construction contractor - Song Da 11 Joint Stock Company said: The excavation and casting of the column foundation has been completed since February 7, 2013. Currently, the contractor has concentrated human resources and machinery and equipment, urgently installing steel poles and stretching wires.

Present at the construction site, General Director Nguyen Manh Hung wished Tet, encouraged employees to participate in the construction, and emphasized that the 220 kV Van Tri - Soc Son transmission line is a project that plays an extremely important role in the construction. prevent overload for 220 kV power grid supplying power to Hanoi capital. The General Director asked the contractor and related units to try to overcome difficulties and make efforts to execute the work to ensure the progress and quality of the items. The project is expected to complete the construction and energizing and put into operation in February 2013.

The delegation of the National Power Transmission Corporation congratulated the officials, engineers and workers on the construction site of the 220kV Van Tri - Soc Son transmission line (Photo: Le Hoan)

It is known that the 220 kV Van Tri - Soc Son transmission line is a double-circuit line, with a length of 27.27 km, 101 pole positions, a total investment of more than 150 billion. The process of implementing the 220 kV Van Tri - Soc Son transmission line project encountered many difficulties and problems, especially problems with compensation and site clearance policies. However, the project still ensures progress thanks to the timely direction of the Government and the effective support of Hanoi city and Soc Son district.

According to the online newspaper Communist Party of Vietnam